The project’s schedule consists of all the tasks that must be executed and the execution logic which is the links between the tasks. Links are the dependencies between tasks, and in other terms – the sequence of tasks.In the next article, we will talk about the types of links between tasks, lags and some say that FF  (Finsh to Finish) links should not be used – is that true or false? Keep reading  -  FF SS

Critical path analysis - MS Project

תמונה
 A questiuon that is asked frequntluy  During critical path management In MS Project  is  what is the critical path or how to view my critical path in MS  Project  ?  The instance will display the list of activities that are considered to be critical in MS Project according to the CPM method (MS Project Critical Path). Want to know more about -   Critical path analysis? Keep reading >>    Critical path analysis

Project schedule sample

תמונה
  The HCP analysis of this schedule yielded insights into the expected success levels of various aspects of the project. Note that all of these estimations are based solely on our conclusions regarding the robustness and integrity of the schedule, without actually analyzing any actual cost or scope data. Click the following link to view HCP-Go >>  Project schedule sample

Critical path analysis - accurate schedule

תמונה
You want your schedule to be accurate. More importantly, you want your schedule to be real. To be exactly as it would be in real life. However, schedules in softwares as MS Project, can do something else, intentionally or unintentionally.  Keep reading MS project case study Examples of critical path analysis

MS project case study and Critical path

תמונה
At first glance, MS-Project looks like Excel. Some of the icons are identical to ones in Microsoft Word and PowerPoint so it should be familiar.  But the feeling is misleading. The big advantage of Project is that the software is user-friendly and part of the Microsoft software suite. But… When looking at  👉   MS project case study   there are many aspects unique to the Project software, which stem from its purpose as a project-building software tool. The purpose of the article is to give some tips to those who work with the software and want to "make life a little easier". To read more about critical path ckick here 👇 Critical path analysis example

MS project case study HCP-Go

תמונה
  HCP analysis has already been performed on more than 200 projects. Even though the same analysis is performed in all projects – the insights that follow are different. Here are some real-life case studies and MS project case studies told by Tal Levanon, from various projects.  The case studies make it possible to understand the different aspects and different meanings obtained from analysis by HCP-Go.  Keep reading MS project case study Critical path analysis example

Examples of critical path analysis - Milestones

תמונה
“Milestones” is a word that you can hear a lot during projects. In the following article, we examine  examples of critical path analysis  and the issue of “Milestones” thoroughly: we will first understand what a "milestone" in a project is, then we will explain how to represent and define it in a schedule. After that, we will examine what types of milestones exist in projects, and we will answer the interesting question - are they linked to subsequent activities? Eventually, we will solve the following 'riddle' - what is the connection between milestones, HCP method and HCP-Go.Read it here:  Examples of critical path analysis - Milestones

Project Shedule

תמונה
The project manager of a luxury tower project in the Tel Aviv area called me. There was no need to build the schedule - just to examine it by HCP-Go, using the HCP method. The project schedule contained 1,100 tasks and was planned to be completed in 600 workdays.It could be printed on 40 A4 pages. What did the HCP-Go analysis find in the schedule? How many paths were found? What can be done with the finding? For all that and more, you can in the article "Is the longest path necessarily the critical path of the project?  Keep reading in the HCP-Go website: Schedule analysis report MS Poject case study Examples of critical path analysis

Examples of critical path analysis - project schedule

תמונה
A project schedule consists of the tasks (activities) to be performed and the logic of execution - the connections between the tasks, which are basically the dependencies of the activities on each other. When you receive a schedule from someone else, you probably wonder what is hidden inside it. When you create a schedule for your project or to submit it to your customer, you want to make sure you did a good job. We have gatherd for you Examples of critical path analysis - click belwo to view the Examples 👇👇👇 Examples of critical path analysis

Examples of critical path analysis - CPM & HCP

תמונה
The issue of risk management is a fascinating issue, in my opinion, and is closely related in HCP-Go. Why? When you think about risk management, one of the first questions asked is - where is the risk? HCP-Go is very helpful in answering this question. When there is a schedule, HCP-Go analysis defines paths: HCP critical paths and hidden critical paths. More than that - who are the tasks which create those paths. On this topic, you can read in the following article by Yehuda Sapir: What is a risk to an engineering  project When building a schedule for a project, the first question is: Well… What is my critical path? The HCP report includes an executive summary, schedule integrity analysis, HCP critical path analysis and keep reading to view - examples of critical path analysis

HCP-Go | Schedule Analysis Report

תמונה
In projects, specifically construction and infrastructure projects, the “buffer” issue is the center of multiple disputes relating to its economic value. HCP-Go rapidly analyzes  the project for you, condenses manual work processes and helps you control your project status in a flash. For more info click here  -  Schedule Analysis Report

MS project case study | HCP-go Project management case studies

תמונה
  HCP (Hidden Critical Path) is an analysis of project schedule networks, Gantts, written in MS Project. The information resulting from the analysis also consists of all the technical issues in the Gantt and the Gantt structure. For any item displayed in the report, you need to ask ‘why?’ – why is it written this way, why did this happen – and the answers shine a spotlight on the project from unexpected directions, allowing you to finish projects on time with the planned contents and set budget. HCP analysis has already been performed on more than 200 projects, Keep reading about 👇  👇 MS project case study

Schedule analysis report

תמונה
The schedule needs to describe the manner in which we are destined to execute the project, in reality. It is not a theoretical exercise in math!  How can I know all of the technical rules? Isn’t there something that can check the technical aspects for me? Schedule analysis report ! HCP Go - Tal Levanon

MS Project case study

תמונה
Project management case studies - HCP analysis HCP analysis has already been performed  on more than 200 projects. Even though the same analysis is performed in all projects – the insights that follow are different. Continue to read the full aritcle and case studies by Tal Levanon  >>  MS Project case study

Critical path analysis examples

תמונה
What’s behind the words Critical Path in project managments? There are two different methods for finding the critical path and, more accurately, both of them include a path called ‘the critical path’ but it is not necessarily identical. One method is called  CPM – Critical Path Method . The other is called  HCP – Hidden Critical Path . Keep reading the full article by Tal Levanon Critical path analysis examples

Examples of critical path analysis

תמונה
  When building a schedule for a project, the first question is: Well… What is my critical path? The critical path in the project – according to the CPM method – is the path that ends on the latest date in the schedule – and any postponement in it, will result in a postponement at the end of the project. The critical path in the project – according to the HCP method – is the longest path in the schedule – the one in which we invest the most working days. Keep reading the full article by Tal Levanon >>  Examples of critical path analysis

Project management case studies

תמונה
Project management case studies - HCP analysis HCP analysis has already been performed on more than 200 projects Even though the same analysis is performed in all projects – the insights that follow are different Here are some real-life Project management case studies  told by Tal Levanon, from various projects