MS project case study and Critical path

תמונה
At first glance, MS-Project looks like Excel. Some of the icons are identical to ones in Microsoft Word and PowerPoint so it should be familiar.  But the feeling is misleading. The big advantage of Project is that the software is user-friendly and part of the Microsoft software suite. But… When looking at  👉   MS project case study   there are many aspects unique to the Project software, which stem from its purpose as a project-building software tool. The purpose of the article is to give some tips to those who work with the software and want to "make life a little easier". To read more about critical path ckick here 👇 Critical path analysis example

MS project case study HCP-Go

תמונה
  HCP analysis has already been performed on more than 200 projects. Even though the same analysis is performed in all projects – the insights that follow are different. Here are some real-life case studies and MS project case studies told by Tal Levanon, from various projects.  The case studies make it possible to understand the different aspects and different meanings obtained from analysis by HCP-Go.  Keep reading MS project case study Critical path analysis example

Project Shedule

תמונה
The project manager of a luxury tower project in the Tel Aviv area called me. There was no need to build the schedule - just to examine it by HCP-Go, using the HCP method. The project schedule contained 1,100 tasks and was planned to be completed in 600 workdays.It could be printed on 40 A4 pages. What did the HCP-Go analysis find in the schedule? How many paths were found? What can be done with the finding? For all that and more, you can in the article "Is the longest path necessarily the critical path of the project?  Keep reading in the HCP-Go website: Schedule analysis report MS Poject case study Examples of critical path analysis

Examples of critical path analysis - CPM & HCP

תמונה
The issue of risk management is a fascinating issue, in my opinion, and is closely related in HCP-Go. Why? When you think about risk management, one of the first questions asked is - where is the risk? HCP-Go is very helpful in answering this question. When there is a schedule, HCP-Go analysis defines paths: HCP critical paths and hidden critical paths. More than that - who are the tasks which create those paths. On this topic, you can read in the following article by Yehuda Sapir: What is a risk to an engineering  project When building a schedule for a project, the first question is: Well… What is my critical path? The HCP report includes an executive summary, schedule integrity analysis, HCP critical path analysis and keep reading to view - examples of critical path analysis

MS project case study | HCP-go Project management case studies

תמונה
  HCP (Hidden Critical Path) is an analysis of project schedule networks, Gantts, written in MS Project. The information resulting from the analysis also consists of all the technical issues in the Gantt and the Gantt structure. For any item displayed in the report, you need to ask ‘why?’ – why is it written this way, why did this happen – and the answers shine a spotlight on the project from unexpected directions, allowing you to finish projects on time with the planned contents and set budget. HCP analysis has already been performed on more than 200 projects, Keep reading about 👇  👇 MS project case study

MS Project case study

תמונה
Project management case studies - HCP analysis HCP analysis has already been performed  on more than 200 projects. Even though the same analysis is performed in all projects – the insights that follow are different. Continue to read the full aritcle and case studies by Tal Levanon  >>  MS Project case study