Project Shedule

תמונה
The project manager of a luxury tower project in the Tel Aviv area called me. There was no need to build the schedule - just to examine it by HCP-Go, using the HCP method. The project schedule contained 1,100 tasks and was planned to be completed in 600 workdays.It could be printed on 40 A4 pages. What did the HCP-Go analysis find in the schedule? How many paths were found? What can be done with the finding? For all that and more, you can in the article "Is the longest path necessarily the critical path of the project?  Keep reading in the HCP-Go website: Schedule analysis report MS Poject case study Examples of critical path analysis

Examples of critical path analysis - project schedule

תמונה
A project schedule consists of the tasks (activities) to be performed and the logic of execution - the connections between the tasks, which are basically the dependencies of the activities on each other. When you receive a schedule from someone else, you probably wonder what is hidden inside it. When you create a schedule for your project or to submit it to your customer, you want to make sure you did a good job. We have gatherd for you Examples of critical path analysis - click belwo to view the Examples 👇👇👇 Examples of critical path analysis

Examples of critical path analysis - CPM & HCP

תמונה
The issue of risk management is a fascinating issue, in my opinion, and is closely related in HCP-Go. Why? When you think about risk management, one of the first questions asked is - where is the risk? HCP-Go is very helpful in answering this question. When there is a schedule, HCP-Go analysis defines paths: HCP critical paths and hidden critical paths. More than that - who are the tasks which create those paths. On this topic, you can read in the following article by Yehuda Sapir: What is a risk to an engineering  project When building a schedule for a project, the first question is: Well… What is my critical path? The HCP report includes an executive summary, schedule integrity analysis, HCP critical path analysis and keep reading to view - examples of critical path analysis

HCP-Go | Schedule Analysis Report

תמונה
In projects, specifically construction and infrastructure projects, the “buffer” issue is the center of multiple disputes relating to its economic value. HCP-Go rapidly analyzes  the project for you, condenses manual work processes and helps you control your project status in a flash. For more info click here  -  Schedule Analysis Report

MS project case study | HCP-go Project management case studies

תמונה
  HCP (Hidden Critical Path) is an analysis of project schedule networks, Gantts, written in MS Project. The information resulting from the analysis also consists of all the technical issues in the Gantt and the Gantt structure. For any item displayed in the report, you need to ask ‘why?’ – why is it written this way, why did this happen – and the answers shine a spotlight on the project from unexpected directions, allowing you to finish projects on time with the planned contents and set budget. HCP analysis has already been performed on more than 200 projects, Keep reading about 👇  👇 MS project case study

Schedule analysis report

תמונה
The schedule needs to describe the manner in which we are destined to execute the project, in reality. It is not a theoretical exercise in math!  How can I know all of the technical rules? Isn’t there something that can check the technical aspects for me? Schedule analysis report ! HCP Go - Tal Levanon

MS Project case study

תמונה
Project management case studies - HCP analysis HCP analysis has already been performed  on more than 200 projects. Even though the same analysis is performed in all projects – the insights that follow are different. Continue to read the full aritcle and case studies by Tal Levanon  >>  MS Project case study